Dear Neighbours

07.08 Update

Hello Neighbours,

I spoke with Jack from AllPoints Fibre yesterday, and it looks like the build on Grays Close is going ahead.

They need to obtain access to OpenReach’s manhole located on Grayswood Road, from which they will thread the fibre through ducting to the beginning of Highercombe Road. From there, they will dig the whole length of Highercombe Road all the way to Grays Close and will use OpenReach’s poles to connect our homes (please see the attached plan Jack provided).

Jack told me that they would need a maximum of one week to complete this. However, the manhole cover is damaged, and they first need to ask OpenReach to clear the access for them. OpenReach is obliged to do this within two months from the request, but it usually takes them around a month. So fingers crossed, if there are no further obstacles, we should be able to order from SwishFibre within six weeks. Jack will provide us with updates at every step.

Note to our neighbours on Highercombe Road and Three Gates Lane: Jack mentioned that there are not enough registrations so far, but they are monitoring them. As soon as the number of registrations crosses the threshold (I’ve been told at least 30%), he will be in touch with all those who registered.

Best regards,
Rafael

Original post

My name is Rafael, and I live at The Oaks Grays Close, Haslemere.
I hope this letter finds you well.

I’m reaching out about the exclusion of our neighbourhood from the broadband upgrade.

I’m not sure if you are aware, but in 2020, Haslemere was fortunate to be included in the nationwide project to upgrade the telecommunication infrastructure to a fibre network. This initiative aims to connect at least 85% of premises to fibre network by 2026, offering a new standard in telecommunication technology.

Initially, our neighbourhood was scheduled to be connected by November 2021. However, due to unexplained delays, the project was postponed several times and ultimately abandoned. As a result, our neighbourhood is among the 15% of premises that won’t be upgraded.


To find out more about fibre, please [click here]

With today’s technology, streaming services replacing satellite broadcasting, traditional landlines being retired in favour of digital lines, and not to mention more tech-savvy technologies like smart homes, the demand for data transfer capacity is much greater than it used to be.

The older, copper line technology already struggles with current demands, and as fibre became a new standard the new digital services facilitate its capabilities, further negatively impacting those whose lines were not upgraded.

For those interested in how fibre compares to copper broadband, here is a quick comparison table based on my current copper provider, and Swish Fibre packages available in Haslemere:

DownloadUploadMonthly cost
My current
copper broadband
24 Mbps5 Mbps£22.00
first 12 months, £35.50 thereafter
Swish Fibre Plan A150 Mbps150 Mbps£28.00
Swish Fibre Plan B400 Mbps400 Mbps£35.00
Swish Fibre Plan C900 Mbps900 Mbps£42.00

Please see the image below, showing the reach, marked in blue, of the fibre network.

Although our neighbourhood is no longer in the plans, there is still a chance for us to get connected.

To give us a chance of being reconsidered in the fibre network plans, the only thing we need to do is register our interest on the websites of three providers serving our neighbourhood. Please note this is a no-obligation registration, and for the most effective outcome, it is advisable to register with all three providers, even if you have registered in the past.

The more of us that register, the greater the chances of our area being reincluded in their future plans.

If you have any questions or need assistance with the registration process, I am more than happy to help. If you would like to discuss it further, please leave a comment below.

I am in contact with Swish Fibre, OpenReach, and our Town and County Councils. Therefore, I would greatly appreciate it if you could let me know whether you decide to sign up. This will help me determine the best time to follow up with my direct contacts and advocate for our inclusion.

Thank you for your time.

Best regards,
Rafael


Let’s chat

  1. Rafael avatar

    Hello,

    If anyone has any questions, or comments please feel free to post them here.

    Thank you

  2. Margaret avatar
    Margaret

    Hello Rafael,

    Thank kindly for your initiative.

    I have registered our interest.

    With kind regards,
    Margaret

  3. Richard Burns avatar
    Richard Burns

    Hi Rafeal

    Thanks for putting this information through, I’d already registered our interest with swish and have registered with the other links as well now.

    I’m hoping this will make it here eventually, I see the cables are dangling from the pole at the entrance to Grays Close.

    Richard Burns
    Falcon Cottage

  4. Rafael avatar

    Hello Margaret and Richard,

    Thank you for registering.

    The cables belong to OpenReach, and they informed me that “all the equipment needed is already there”, so it was a surprise when they withdrew from the installation.
    Let’s hope we can encourage them or Swish to reconsider.

    Best regards,
    Rafael

  5. craig langley avatar
    craig langley

    Hi Rafael,
    I have registered on all the sites.
    Thanks again for doing this.
    Regards,
    Craig
    Zoe Cottage

  6. Rafael avatar

    Hi Craig,
    Thank you so much for letting me know.
    Cheers,
    Rafael

  7.  avatar
    Anonymous

    Hi Rafael,

    We have also registered with all the sites. Thank you for trying to sort this out.

    Regards,

    Alison

  8. Rafael avatar

    Hi Alison,

    That’s great. Thanks for the info.

    Cheers,
    Rafael

  9. Hi Rafael, thank you for organising. I’m in the blue shaded area, near the top of Three Gates Lane. We have what i think is FTTC, which means the connection is limited to around 100 meg. Would be great to have more bandwidth. I registered with all of the sites listed. We waited more than 6 years for the FTTC connection and have seen this area consistently experience delays in promised rollouts (ISDN, Broadband, etc…). Please let us know if there is anything else we can do beyond just registering interest.
    Thanks again.

  10. Rafael avatar

    Hi David,

    Thank you so much for reaching out.

    Next week, I’ll contact all three providers, asking them to check the number of registrations and see if it’s enough for them to reconsider the rollout. I’ll post the updates here as soon as I hear back from them. As far as I can tell, there is nothing more we can do, so let’s just hope there will be enough registrations of interest for them to make this project viable.

    It’s interesting that you are within the blue area and still can’t get FTTP. OpenReach told me that their nodes have capacity limits, so maybe even if they get cables to a street, they may not be able to offer connection to all of the residents on that street.

    Either way, I’m sorry to hear that. I really hope we can still change this.

    Thank you again for your message, it is really helpful.

    Best regards,
    Rafael

  11. Richard avatar

    I had the following email from All Points Fibre, so we’re close it seems.

    Dear Richard,

    My name is Jack, part of the Community Engagement team here at AllPoints Fibre.

    First of all – Thanks so much for registering your interest for our service! We’re keen to get as many Haslemere residents on our network, so I’ll cut to the chase on how we can get Grays Close to the top of the priority list.

    I’ve put together a proposal for our design teams and will let you know as soon as I have a response. On your side, we’re only missing registers of interest from 3 properties from Grays Close (The Cedars, Westering, Chantry House), so if you could speak to your neighbours to see if they would be willing to add their interest, that would make our case even stronger.

    I will keep you and your neighbours informed about our progress. I will be in the Haslemere area next week so if you would like a bit more information about the build process, or anything Fibre related, please let me know.

    I look forward to getting back to you soon,

    Best wishes,

    Jack W-Stacey

  12. Rafael avatar

    Hi Richard,

    I was just about to post the update, as I received the same email as well. It seems they sent it to everyone who has registered.

    I’ll get back to him and my contacts at All Points Fibre and will post an update here with the time and date when Jack will be around, so anyone interested can join for a chat.

    Cheers,
    Rafael

    1. Richard avatar

      Thank Rafael, it’s much appreciated.

  13. Rafael avatar

    Hello everyone,

    Jack from AllPoints Fibre will come to survey Grays Close on Wednesday afternoon, if you are interested in asking him some questions.

    If you won’t be able to make it, please feel free to post them here, and I’ll try to get answers from him for you.

    Cheers,
    Rafael

    1. Richard avatar

      Thanks Rafael, the only question I have is if they don’t change their plans and we aren’t in the rollout to 2026 will it then be installed after 2026 or is the exclusion indefinite?

      I’ll be around Wednesday afternoon so will keep an eye out and come out when he is here as well.

      Many thanks

      1. Rafael avatar

        Based on what OpenReach told me, the fibre rollout is not an obligation, and the 85% by 2026 is OpenReach’s own internal goal. The Government’s target is 99% by 2030, but it’s just a target, and it has already changed from 2025. So, I guess there is a chance we would get it in the end, but when?

        I’ll try to get a more specific time from Jack tomorrow and post it here.

        Cheers

  14. Thanks for sending this out, Rafael- I’ve followed the instructions and signed up at both the links for home address

    1. Rafael avatar

      Hello James,

      Thank you very much for joining and letting me know.

      Many thanks,
      Rafael

  15. Rafael avatar

    Hello,

    Jack from AllPoints Fibre will be on Grays Close at 6pm Wednesday.

    Cheers,
    Rafael

  16. Richard avatar

    That’s great news Rafael, thanks for all your efforts to make this happen.

    We’ll be ordering as soon as it’s available.

    1. Hi Richard,

      No problem at all, I’m really glad it worked so quickly.
      I’ll be ordering right away as well.

      Cheers.

  17. Hello,

    Quick update from AllPoints Fibre:

    Good morning Rafael,

    I have good news! Openreach have agreed to fix the seized chamber on Grayswood Road, and the estimated completion date is the 10th September.

    As soon as we have confirmation that the chamber is fixed, I’ll be able to give you a build schedule for Grays Close.

    Best wishes,
    Jack

  18. Hello,

    Quick update for everyone interested: It looks like OpenReach is planning to fix the chamber on the 11th of September.

    Cheers,
    Rafael

    https://one.network/?GB139981434

Please leave a message

Feel free to comment or ask a question.